Pexgol Elbow for Slurry Transport

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Case Study Nº

109

Customer

Antioquia Gold
Colombia

|

2022

Working Conditions

Fluid: Sludge | Temperature: 40°C / 104°F

Pexgol Pipes

Pexgol 45° elbow 160 mm, class 15 | GP flanged coupling 160 mm

Application

Slurry transport

Lenght

n/a

Categories

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE

The Challenge

Antioquia Gold, a Colombian mining company, required continuous maintenance to the HDPE pipe (160 mm PN16) that they used for the discharge to the FALCON 1 gravimetric concentrator, which suffered from constant abrasion problems. It had to be thermo-fused in very short sections to give the necessary radius of curvature in the operation. This pipe had a durability of 1 to 2 months maximum.

Pexgol Solution

Due to its durability, ease of installation (mechanical) and because it does not require maintenance, Antioquia Gold decides to use a Pexgol elbow.

The elbow was installed and after 90 days of testing, the elbow and the connections have maintained hermeticity without fluid loss, maintaining the integrity and initial conditions during the period of operation, when subjected to the expected conditions.

Thanks to the benefits of Pexgol elbows and the versatility of the GP flange coupler, the tolerance of the elbow and its easy handling, the operation cuts were carried out satisfactorily. The elbow was installed by simply aligning the mechanical flanges, making the installation complete in 20 minutes.

Related Case Studies

Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015