Transport of Muddy Water in a Palm Oil Processing Plant

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Case Study Nº

85

Customer

La Gloria
Colombia

|

2020

Working Conditions

Temperature: 80°C | Flow: 36m³/h

Pexgol Pipes

Pexgol 110 mm (4″), clase 12

Application

Muddy water transportation

Lenght

1200 m

Categories

Transport of Muddy Water (Pome) witha High Content of Organic Load.

The Challenge

La Gloria, a company dedicated to the extraction of palm oil in César (Colombia), required a new line to transport muddy water to the oxidation ponds. From the florentino lagoon (treatment pool), passing through the main road and the plantation, the excavation and installation of the pipe had to be carried out in the crop, between palms without causing damage to the plants and the irrigation pipe. In addition, given the operating conditions and the type of fluid, a pipe was required that resists high temperatures and has a low internal roughness index due to incrustations.

Pexgol Solution

Due to the high costs of carbon steel pipe, added to the cost of assembly, it was decided to use Pexgol pipes.

Pexgol was selected for its quick and easy installation, fewer joints and the possibility of supplying it in rolls.

The installation of the 1200 meters was carried out in 4 hours. Four electrofusion joints were used for the splicing of the sections and a mechanical joint was used at each end.

Related Case Studies

Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019