Extraction of Underground Water

Extraction of underground water through wells

Case Study Nº

24

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2010

Working Conditions

Extreme environmental temperatures (-25°C to 40°C).

Pexgol Pipes

Pexgol 280 mm, Class 10.

Application

Underground water extraction.

Lenght

200 m.

Categories

Extraction of underground water through wells

The Challenge

Collahuasi Mine extracted process water through wells, they used a galvanized steel pipe. This pipe had several failures on its joints and demanded a long time installation process (around 3 days).

The client required a more flexible pipe, with longer working life than the steel, in order to keep the operations stable and minimized the stops in the plant for maintenance.

Pexgol Solution

A Pexgol pipe was installed in less than 3 hours, reducing 24 times the average installation time. Its weight was lighter than steel (70% less), so it involved less workers, less tolls, and less equipment to leave the well full operative. During the working life of the well, the Pexgol pipe didn’t require any sort of maintenance, and it was employed after in another application at the plant.

Related Case Studies

Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018