Case Study Nº

61

Customer

Ferrexpo Yeristovo Mining
Ukraine

|

2019

Working Conditions

Vertical installation, ground laying on hills. Ambient temperature: -15°C to 4°C

Pexgol Pipes

Pexgol 280 mm (10”), Class 15

Application

Mine Dewatering

Lenght

360 m

Categories

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

The Challenge

Ferrexpo Yeristovo Mining needed to install mobile long sections of pipeline for mine dewatering. They requested that the pipe should have scratch resistance and can be installed on the rocks without any complicate preparations.
They used to work with steel pipes but they presented serious problems such as:

  1. Corrosion
  2. Difficult and expensive installation
  3. Long disassembly and replacement time

Pexgol Solution

The client chose Pexgol pipes with 280 outside diameter, class 15 in coils of 120 meters each with mechanical couplers for a fast and efficient installation. During the installation a 60 ton Hitachi bulldozer and a Manitou telehandler were used for decoiling.

There were 3 separated lines of one piece of 120 meters each without any additional connectors. The only connection was a flange coupler with a pump outlet. Pipes were fixed on top and in the middle by fixpoint clamps as well.

The use of Pexgol pipe solutions allow the client to save costs (manpower and installation time).

Related Case Studies

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019